May 4th Maintenance
Scheduled Maintenance Report for Vertical Response
Completed
The scheduled maintenance has been completed.
Posted May 05, 2023 - 06:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 04, 2023 - 19:00 EDT
Scheduled
The primary data center for VerticalResponse has scheduled a maintenance window beginning Thursday, May 4th at 1900 EDT and lasting until 0600 EDT Friday, May 5th. During this overall maintenance window there will be a smaller period of several hours where the VRC and VR2 will be unavailable for login. During this time scheduled campaigns will still send as normal.
Posted May 04, 2023 - 10:40 EDT
This scheduled maintenance affected: Vertical Response (VR2) (Website, Email Campaigns, Email Automations, Landing Pages, Third-Party Integrations, API, Salesforce Plugin) and Vertical Response (Classic) (Website, Email Campaigns, API).